The
following are the sequence of work for Critical Personnel Crossing but not
limited to this:
a)
Application
of Permit To Work (PTW)
Permit to Work (PTW)
shall be applied and discussed at the early stage of Project Signboard
construction works. C0ntractor's personnel shall work closely to CLIENT
representative and to comply all their requirement. Apart from that, Contractor’s
personnel shall ensure the construction of Project Signboard will use the IFC
drawing.
Tool box meeting on
daily basis shall be carried out by safety personal prior to start work. The
safety personal shall highlight the potential hazard of the work to be done
according to the Job Hazard Analysis (JHA). Safety personal shall ensure the
JHA produce are discussed and review with CLIENT according to their respective
sequence of works and to be attached with the PTW.
b)
Survey
works
The survey team shall
ensure all marking/pegging made are clearly visible and recheck as to ensure
the correct location of Project Signboard. Reference level shall be established
at any existing permanent structure. Any issues with regards to the survey works
must be cleared prior to start/continue any construction works.
c)
Delivery
of construction material
Construction material
such as RHS (100mmX50mmX3mm THK), timber board, metal ladder, power hand drill
etc. shall be stored and unload to the nearest working area. The temporary
stored area shall be barricaded and proper signage to be displayed surround the
area.
d)
Assemble
of Project Signage
Prior to column pole
concreting works, the Project Signages in which consist of Timber Board (12 mm
THK) and RHS (100mm x 50mm x 3 mm THK) are to be manually assemble. The Timber
Board will be drilled directly to the RHS as for the main support. Site
Personnel to ensure the dimension and spacing of Timber Board are according to
the IFC Rev 0 drawing.
e)
Construction
of column pole and Bracing
The excavation of
column pole will be done manually as to avoid any underground utilities
affected during the construction works. Site personnel shall ensure the
foundation hole are excavated correctly, for the rolled hollow section column
(375 mm x 375 mm x 750mm Depth). The Project Signages which already assemble
will be lifted manually to the excavated column pole are. The verticality and
alignment of the Project Signages shall be check prior to pour concrete and
additional bracing should be considered during the installation of RHS column.
Once the Column pole
are concrete, the construction works should continue with the excavation of bracing
pole. The top bracing will be installed manually to the erected project
signboard using the metal ladder and drill machine.